  • Ukraine’s Ministry of Infrastructure has announced a project to build a tunnel under the Dnipro River in Kyiv as an alternative to bridges that are vulnerable to Russian attacks.
  • The project was initiated amid intensifying attacks on Ukrainian infrastructure, but its implementation, timeline, and cost are the subject of debate among experts.
Construction of a tunnel under the Dnipro River in Kyiv

This fall, Russia intensified its attacks on Ukrainian infrastructure, targeting bridges across the Dnipro River in particular. For Kyiv, this is a particularly dangerous scenario: a reliable connection between the Right and Left Banks is essential not only for the daily movement of millions of people but also for the functioning of urban logistics and critical services.

 
Adv

Against this backdrop, the Ministry of Infrastructure announced plans to develop a project for a tunnel under the Dnipro River. However, whether such a large-scale project can actually be implemented under current conditions – and whether the costs are justified – remains an open question.

Will the tunnel truly be a reliable alternative to bridges? How many years and how much funding might its construction require? And does Kyiv risk ending up with yet another exorbitantly expensive project without a clear justification? 24 Channel investigated.

popular videos

Advertisement

As early as the beginning of October, the intensity of Russian attacks on the capital’s bridges reached nearly its peak – during that time, the occupiers shelled the structures six times in just three days. At the time, the American newspaper The New York Times noted that Kyiv’s bridges are of strategic importance to the capital, as they facilitate daily traffic between the two banks of the Dnipro River.

Kyiv Mayor Vitali Klitschko shows the aftermath of Russian strikes on one of the capital’s bridges – watch the video:

The Left Bank is home to large residential neighborhoods where about one million people live, while the Right Bank is where a significant portion of government agencies and businesses are concentrated. Therefore, damage to the bridges could disrupt not only residents’ daily commutes but also the operations of vital city institutions.

Advertisement

Attacks on bridges are just part of Russia’s broader campaign against Ukrainian infrastructure. Energy facilities, railways, industrial enterprises, warehouses, data centers, and medical logistics are all under attack.

In this situation, disruptions to crossings over the Dnipro could have consequences far beyond mere traffic jams: the capital’s bridges are used to transport food, equipment, and other essential cargo that must flow uninterrupted from one bank to the other.

The latest attack occurred on the night of November 17, 2026. According to Volodymyr Zelenskyy, the Russians fired four ballistic missiles at the South Bridge and three more at the North Bridge. After the strikes, traffic on both bridges was temporarily restricted, causing a traffic collapse on several of the capital’s major thoroughfares. Traffic was later partially restored.

Advertisement
The status of Kyiv’s bridges as of November 18, 2026 / Photo: Kyiv City State Administration

Against this backdrop, the idea of building a tunnel under the Dnipro River in Kyiv has emerged, a proposal publicly raised by People’s Deputy Oleksandr Kachura during “Question Time with the Government.” Among the arguments in favor of the project, he cited the constant Russian strikes on the capital’s bridges and the need to create an alternative connection between the riverbanks.

“Tonight’s strikes on the South and North Bridges once again confirm just how urgent this project is. We must act immediately! People’s lives, the functioning of the economy, and military logistics all depend on a reliable connection between the two banks,” Kachura wrote in a Facebook post.

Advertisement

Subsequently, preparations for construction were also discussed at the government level. Mykola Kalashnyk, Ukraine’s Minister of Recovery, Infrastructure, and Transport, held a working meeting dedicated to the potential tunnel under the Dnipro River. According to him, constant Russian attacks on the bridges are forcing us to seek alternative routes and strengthen the resilience of the capital’s transportation system.

The enemy continues to strike the capital’s bridges, so we must create alternative routes and strengthen the resilience of the transportation system. This is a strategic decision that affects not only people’s daily commutes but also the operations of businesses and urban logistics. We need to start preparing such a project right nowthe minister emphasized.

Mykola Kalashnyk and Oleksandr Kachura at a meeting on the project / Photo: Oleksandr Kachura’s Facebook

The American company Robbins, which specializes in the production of tunnel-boring equipment, was also involved in the discussions. Its representatives discussed possible technological solutions and next steps with the Ukrainian side. According to Kachura, the company is ready to provide equipment, train Ukrainian specialists, and ensure technical support for the work.

Advertisement

The MP also released an official document outlining a proposal for the construction of tunnels in Ukraine. However, the Americans’ involvement at this stage does not mean that the project has already been approved, funded, or is ready for implementation. For now, the discussion is limited to preliminary consultations and the evaluation of technical feasibility.

Document regarding the proposal from the American company / Photo: Oleksandr Kachura’s Facebook

The construction timeline sparked a separate debate. Oleksandr Kachura stated that the project could be completed in just a few months. After facing criticism of these estimates, the lawmaker clarified that he was referring specifically to tunneling work.

“It’s not years – the implementation of this project is measured in months – because they have this technology,”– Kachura quoted his own statement in an interview with “Apostrophe.”

Advertisement

A letter from Robbins’ vice president, which the MP published, does indeed mention a timeframe of 3 to 12 months. However, there is an important detail: this is the estimated duration of the tunneling work specifically, not the entire construction cycle. Before that, the tunnel’s route and parameters must be determined, geological and hydrogeological surveys must be conducted, a feasibility study must be prepared, and funding must be secured.

Minister Kalashnyk himself reported that Robbins is to provide proposals regarding the necessary studies, equipment, and potential partners. Based on these, the Ukrainian side will be able to proceed to more detailed technical and financial calculations.

At the same time, transportation planning expert Dmytro Bespalov told 24 Channel that it is too early to talk about construction in a few months. According to him, the American company did not promise to build the tunnel within that timeframe – it merely estimated the time it would take for its equipment to potentially cover the necessary distance.

Advertisement

Moreover, they have not yet assessed the geology or hydrogeology of the site. Nothing. By global standards, the construction of such a tunnel would most likely take somewhere between 5 and 10 years. In other words, in the current situation, it is unlikely to be of any help to us– Bespalov noted.

The expert also urges against diverting limited engineering and financial resources to long-term projects that will not yield quick results. In his opinion, the priority right now should remain the restoration and repair of existing major bridges.

An equally important issue is the cost. Mykola Kalashnyk estimated the construction of the simplest road tunnel – without a metro line – at approximately 500 million euros. He also reported on preliminary negotiations with the European Investment Bank regarding the possible allocation of 100 million euros to kickstart the project.

Since it will be difficult to finance such a project solely from the Ukrainian budget, the government is considering the participation of Ukrainian, European, and American partners.

Against this backdrop, there are certain questions surrounding Kalashnyk, and it is unclear whether he will remain minister, as he has found himself in the spotlight due to Operation Carthage. In particular, the controversial businessman Vladislav Sokolov (the very same one who in his penthouse kept a live crocodile and had no filter on social media) accused the minister of failing to fulfill financial agreements dating back to the time when Kalashnyk headed the Kyiv Regional State Administration, and Sokolov’s companies were involved in the construction of protective structures for energy facilities. Obviously, Kalashnyk denies everything. However, his former deputy, Ruslan Oliinyk, added “fuel to the fire” by stating that the minister is well acquainted with Sokolov and that it was Kalashnyk himself who botched the construction of the protective structures in the Kyiv region.

For Kyiv residents, who have been schooled by stories of the capital’s numerous “long-delayed construction projects” – such as the metro lines to Troieshchyna and Vynohradar, the Podil Bridge, the Darnytsia Railway Station, and so on – it is precisely the issue of money that traditionally sparks skepticism.

The estimated cost of 500 million euros has already sparked a debate over whether the future tunnel is too expensive for Ukraine. Blogger Yuriy Nikolov pointed to a Norwegian project for a 27-kilometer-long road tunnel, the construction of which is estimated to cost $2.4 billion. According to his calculations, that works out to about $90 million per kilometer. Moreover, the tunnel is to be built at a depth of about 400 meters.

Against this backdrop, the journalist believes the cost estimate for the Ukrainian project appears disproportionately high. Nikolov roughly estimates the width of the Dnipro River in Kyiv, adds the length of the approach and exit ramps, and arrives at a figure of approximately $300–600 million per kilometer of tunnel. He emphasizes the contrast: this involves construction under a relatively shallow river, not at a depth of hundreds of meters.

However, his calculation is tentative: it is based on assumptions about the length of the tunnel and access roads, rather than on a finalized design or a detailed cost estimate. Moreover, these estimates come from a blogger who does not have a deep understanding of the subject (as he himself admits).

Urban planner Dmytro Makogon considers such a comparison to be inaccurate. He explains that the cost of infrastructure projects depends not only on their length but also on geology, technology, supporting infrastructure, and construction requirements. In his view, it is impossible to compare two projects based solely on the price per kilometer if the conditions and scope of work differ.

To illustrate his point, Makogon cites the example of housing construction. He says that anti-corruption activists once asked him to compare the cost of government-subsidized housing with prices in new private developments. But it turned out that they were comparing finished, fully finished apartments with housing at the foundation or skeleton stage, which is sold to investors with certain risks. Moreover, public construction involves different documentation requirements.

The basis for comparison here is even lower. For example, many tunnels are built in Norway because it’s easier there – due to the geology and the industry that has developed accordingly. I think the 500 million figure cited for the tunnel under the Dnipro is just a rough estimate, and the actual cost will be higher. But people can already start pushing the outrage– noted the urban planner.

So for now, the debate centers on a figure that is not yet based on a fully developed project. To assess how reasonable the 500 million euros figure is, we need the results of geological surveys, a feasibility study, and a detailed cost estimate. Without them, both claims of excessive cost and assurances of the expenditure’s feasibility remain premature.

Despite all the debate, the tunnel is viewed not only as a potential way to secure the capital’s transportation links but also as a long-term infrastructure alternative to bridges.

Serhiy “Flash” Beskrestnov, an advisor to the President of Ukraine on the development of defense technologies, believes that Kyiv truly needs such a facility. At the same time, he acknowledges that, even with the support of international partners, construction could take several years.

But what if the bridges sustain critical damage sooner? Ferry and pontoon crossings are among the possible temporary solutions mentioned. Beskrestnov, however, is skeptical about their effectiveness on the scale of a large city.

According to him, a ferry crossing can only serve as an emergency solution for transporting critically important cargo, as its capacity would be extremely low. In addition, it requires shore piers and access roads – structures that would remain vulnerable to missile strikes and drones.

A pontoon crossing also requires separate access roads and transportation interchanges. Even if it can be set up quickly, this does not guarantee stable operation during attacks. As Beskrestnov notes, a single hit from a Shahed kamikaze drone is enough to put such a structure out of commission.

Of course, the military must have a contingency plan, and it’s good that they’re thinking about itthe presidential adviser emphasized.

At the same time, he warns: if the enemy manages to destroy all of Kyiv’s bridges, pontoon and ferry crossings will also come under attack. Therefore, they should not be considered a full-fledged replacement for bridges. The resilience of the transportation system, in his view, depends first and foremost on protecting the skies – strengthening air defense and electronic warfare capabilities.

A tunnel under the Dnipro River could indeed become an important alternative to bridges for Kyiv, but between a high-profile idea and its implementation lie years of work, complex engineering solutions, and hundreds of millions of euros. Without research findings and a transparent cost estimate, it is difficult to assess how justified such expenditures would be. At the same time, the issue of the capital’s transportation resilience cannot be put on hold. So we’ll have to wait and see whether this initiative moves beyond high-profile announcements to concrete calculations and actual construction work.